Project List:
|
| |
Back to the top
Millport Slough Bridge
Owner: ODOT
Value: $11,476,583
Dates: 9-09 to 11-21-11
This project, which includes more than 600 driven piling, was constructed over Millport Slough on US Highway 101 between the Pacific Ocean and a national wildlife refuge. Accordingly, this job contains stringent environmental standards. |
|
 |
| |
 |
|
 |
| |
|
|
 |
|
 |
| |
|
|
 |
|
 |
| |
|
|
 |
|
 |
| |
|
|
 |
|
 |
| |
|
|
 |
|
 |
| |
|
|
 |
|
|
Back to the top
US26-Mckay Creek
Owner: ODOT
Value: $4,093,446
Dates: 6-14-10 to 6-30-11
This project consists of the demolition of two old bridges, construction and removal of two detour bridges, and the construction of two new bridges on US Hwy 26 west of Portland, OR. |
|
 |
| |
 |
|
 |
| |
|
|
 |
|
 |
| |
|
|
 |
|
|
Back to the top
Naval Center Demolition
Owner: NAVFAC Northwest
Value: $687,989
Dates: 9-09-10 to 11-15-10
This project included the demolition and re-grading of a three and a half acre site in Eugene, OR. Work elements included asbestos and lead surveying, abatement, and demolishing over 30,000 square feet of buildings. |
|
 |
| |
|
|
 |
|
 |
| |
|
|
 |
|
|
Back to the top
Rufus Landing
Owner: Corps of Engineers
Value: $941,819
Dates: 9-30-09 to 5-20-10
This was a Design-Build project performed for the Army Corps of Engineers. The project consisted of the complete design and re-construction of 1.3 miles of frontage road along the Columbia River near the John Day Dam. |
|
 |
| |
|
|
 |
|
 |
Back to the top
Past Projects
Tenasillahe Island
Owner: Corps of Engineers
Value: $620,000
Dates: 4-1-07 to 9-15-07
This design build project consisted of tide-gate retrofitting and the construction of two small pre-cast bridges. The project was logistically challenging because it was on an island in the middle of the Columbia River.
 |
|
 |
Back to the top
Siletz River Bridge
Owner: Lincoln County
Value: $3,753,219
Dates: 5-08 to 10-09
This project consisted of road and bridge construction. The bridge was a 360'x36' BT84 Precast Girder Bridge, and the roadwork included excavation, grading, paving, and storm drainage. |
|
 |
| |
 |
|
 |
| |
|
|
 |
|
|
Back to the top
|
| |
|